Gantt Chart
The Gantt Chart is the project's interactive schedule. You create tasks with start and finish dates, link them with dependencies, assign resources, and mark milestones — all laid out on a horizontal time axis. Tasks that fall on the critical path are highlighted so you can see at a glance what is driving the finish date.
Sidebar location: Track → Gantt Chart (
/projects/gantt-chart).
What you can put on the schedule
- Tasks — units of work with a Start date, a Finish date, and an optional Resource (owner).
- Milestones — zero-duration markers for events such as PDR, CDR, or ship.
- Dependencies — links between tasks so that one task's timing constrains another.
- Resources — the person or team responsible for a task.
Walkthrough
- Open the Gantt Chart from Track → Gantt Chart. The current schedule loads on the time axis.
- Click Add task. Enter a Name, set the Start and Finish dates, and assign a Resource.
- To create a milestone, add a task and mark it as a milestone (zero duration). It renders as a diamond on the timeline.
- Add Dependencies between tasks so the schedule reflects the real order of work. Dependent tasks shift when a predecessor moves.
- Read the timeline. Critical-path tasks — the chain with no slack that sets the project finish date — are highlighted.
- Adjust dates or resources as the plan evolves; the timeline updates to reflect the change.
AI Assistant prompts
Suggest a draft schedule for this project based on the requirements baseline and a target ship date of 2026-09-30.
Which tasks are on the critical path right now, and why?
Identify tasks that look likely to slip given their duration and dependencies.
Tips
- Anchor to milestones first. Set PDR/CDR/ship, then fill in the tasks between them — it keeps task-level changes grounded.
- Keep dependencies honest. A missing dependency hides real schedule pressure; the critical-path highlight is only as good as the links you draw.
- Drive risk analysis from here. Once tasks carry three-point estimates, the Schedule Risk Monte Carlo can quantify how likely the finish date really is.